Ho Tin marine Projects

 

 

 

Hong Kong Marina Club, Phase 2 – Jetties A & B Replacement Works

Employer: Hong Kong Marina Club

Value: HK$20 million

Completion Year: 2006

Project Specific: Project includes the replacement of existing timber pile and decking system with pipe piles and concrete pontoon system. Two jetties of about 200m long with 36 fingers for berthing of 72 boats varied from 24m to 14m. Ho Tin is responsible for design and certification of berthing piles (66 nos.), concrete floating pontoons system for Contractor’s design and built package.

Site Photo(s):